Jumping Creek Road Upgrade

The Jumping Creek Road Upgrade is a major project to reconstruct the entire length of Jumping Creek Road, from Ringwood-Warrandyte Road in Warrandyte to Homestead Road in Wonga Park.
Update: April 2025
The project has reached an exciting new milestone: contractors have been appointed, and the works are planned to begin in late April. The initial works will include the construction of the Yarra Road footpath, along with early site investigations on Jumping Creek Road and Dudley Road.
We anticipate some temporary disruptions to the community during these works.
In preparation for the main construction works, we’re working closely withContinue reading
The Jumping Creek Road Upgrade is a major project to reconstruct the entire length of Jumping Creek Road, from Ringwood-Warrandyte Road in Warrandyte to Homestead Road in Wonga Park.
Update: April 2025
The project has reached an exciting new milestone: contractors have been appointed, and the works are planned to begin in late April. The initial works will include the construction of the Yarra Road footpath, along with early site investigations on Jumping Creek Road and Dudley Road.
We anticipate some temporary disruptions to the community during these works.
In preparation for the main construction works, we’re working closely with our contractors to finalise a construction methodology that minimises any impacts on residents.
Questions?
Contact us on 9840 9333 or at manningham@manningham.vic.gov.au.
-
Project update - April 2023
Share Project update - April 2023 on Facebook Share Project update - April 2023 on Twitter Share Project update - April 2023 on Linkedin Email Project update - April 2023 linkFollowing our previous communication, we held four public information sessions in March 2023. The sessions were very successful, and we had a number of residents, business owners and road users attending the sessions. We appreciate the time you spared to come to the sessions. These sessions provided an opportunity for the public to not only become aware of the outcome of numerous events and sessions held before leading us to get to this point but also be informed about the Council plan on how the project construction phase would progress and be executed.
During the sessions, we received a few queries asking for another afternoon session to be held, providing an opportunity to the public who were not able to join us in the March events. We are delighted to inform you that we have organised another session to be held on May 16th at Wonga Hall between 4:00 PM to 8:00 PM.
Details of the session can be found here: Your Say Manningham Letter/Public Session
You can view the proposed design here: Your Say Manningham - Jumping Creek Road - Plans
Please feel free to leave any comments in the feedback/Q&A box below or, following the link leave your question here, and a member of the team will contact you to discuss the project.
-
Project update - Feb 2023
Share Project update - Feb 2023 on Facebook Share Project update - Feb 2023 on Twitter Share Project update - Feb 2023 on Linkedin Email Project update - Feb 2023 linkWe are delighted to inform you that the detailed design for the Jumping Creek Road Project is nearing completion. The design aims to improve road safety, create a recreational trial whilst preserving the natural look and feel of the area.
You can view the proposed design here: Your Say Manningham - Jumping Creek Road - Plans
Also, we are pleased to inform you that the wildlife protection netting installation is completed, and wildlife monitoring devices are coming next. In addition, the planting between the Warrandyte roundabout and Nelson Drive Northern side is completed. Also, preparation of the Southern side of this section is completed, and planting is planned for the next planting season. While we are focusing on the current works, it was not forgotten that trees had been removed a few years back while constructing the bridge. At the time of bridge construction, the seed had been taken from native and indigenous trees and grown in the Friends of Warrandyte State Park Nursery. The number of 300 grown-up trees had been planted around the bridge in August 2022 to cover the loss.
Furthermore, the footpath from Warrandyte roundabout to Nelson Drive has been reconstructed to address the public concern regarding the effects of the footpath constructed as part of stage one works. The footpath works will be continued with the next stages of construction planned to be started in the second quarter of 2023.
Public drop-in information sessions are planned to be held from the 20/03/23 till the 23/03/23 and will allow anyone interested to provide further feedback and or information on the project. Details of the session can be found here: Your Say Manningham Letter/Public Sessions
We aim to make our beautiful Jumping Creek Road safe for road users and more attractive for visitors to encourage their travels and support the local businesses and economy.
Please feel free to leave any comments in the feedback/Q&A box below or, following the link leave your question here, and a member of the team will contact you to discuss the project.
-
Project update - May 2022
Share Project update - May 2022 on Facebook Share Project update - May 2022 on Twitter Share Project update - May 2022 on Linkedin Email Project update - May 2022 linkThe Jumping Creek Road Design Proposal was endorsed by Council on 26 April 2022.
We developed a concept plan for the project and asked for feedback from community during October 2021.
Community feedback helped guide the design and make sure there are minimal impacts on the character of the area.
The design proposal includes:
• Upgrading the Wonga Park Township intersection with traffic lights (Dudley Road and Jumping Creek Road).
• Installation of an underground drainage system including kerb and channel for the entire road.
• New roundabouts at Hooper and Hartley Roads.
• A recreational trail on the northern side of the road.
• Extensive revegetation along the entire Jumping Creek Road corridor.
• Installations of aerial and wildlife crossings to protect wildlife.
Jumping Creek Road has a historically high levels of crashes, including 17 resulting in casualties and one fatal crash between 2009 and 2013.
We believe the upgrade is vital to improve safety for many of our community who use the road to travel to home, work, school and social connections.
The road carries more than 8,100 vehicles per day, with the traffic volume expected to increase to 15,000 vehicles per day by 2035.
When does the upgrade begin?
We completed the first section of the road upgrade between Ringwood-Warrandyte Road and Nelson Drive in Warrandyte in 2020.
The next phase of major works are expected to begin in early 2023, with some early beginning in late 2022.
How can I stay up-to-date with this project?
For the most up-to-date information about this project please subscribe to this project page.
-
Information Sessions 2022
Share Information Sessions 2022 on Facebook Share Information Sessions 2022 on Twitter Share Information Sessions 2022 on Linkedin Email Information Sessions 2022 linkJumping Creek Road has reached a significant milestone, the concept design for the project is now complete. Manningham is pleased with the feedback we gathered from our community consultation, which helped guide the design and ensure impacts on the character of the area were minimised.
We thank everyone for their feedback which has been incorporated. We are now moving onto the next phase of the project to develop the detailed design.
We’re upgrading:
• Wonga Park Township intersection with traffic lights (Dudley Road and Jumping Creek Road)
• Installation of an underground drainage system, including kerb and channel for the entire road.
• New roundabouts at Hooper and Hartley Roads.
• A recreational trail on the northern side of the road.
• Extensive revegetation along the entire Jumping Creek Road corridor.
• Installations of aerial and wildlife crossings to protect wildlife.
We look forward to commencing work on this important project.
For more information or to stay informed, visit yoursay.manningham.vic.gov.au/jumping-creek-road-upgrade. Also, you can view the latest project updates here; and the letter to residents here.
-
Public Consultation
Share Public Consultation on Facebook Share Public Consultation on Twitter Share Public Consultation on Linkedin Email Public Consultation linkDear Your Say members,
RE: Jumping Creek Road project, Public Consultation
In October 2021, Council undertook consultation with the community regarding the proposed designs for the Jumping Creek Road project. Council is currently reviewing the feedback received in liaison with community representatives and the community reference panel.
We anticipate providing further information early in the new year, including further opportunities to meet and discuss the project outcomes prior to proceeding further.
We wish you and your loved ones a Merry Christmas and Happy New Year.
Regards
Manningham Council
-
Concept Design Virtual Drop-in Sessions
Share Concept Design Virtual Drop-in Sessions on Facebook Share Concept Design Virtual Drop-in Sessions on Twitter Share Concept Design Virtual Drop-in Sessions on Linkedin Email Concept Design Virtual Drop-in Sessions linkThe first stage of the Jumping Creek Road upgrade is compete, and now the concept plans for the remainder of the project are now ready. We anticipate the detailed design process to be complete by late 2021, with works to commence late 2022.
You can view the latest project update here, and the 3D Artist impressions here.
We are running these virtual drop-in sessions to share the concept designs with the wider community.
- Session 1: Thursday 21 October, 6.00pm to 7.30pm
- Session 2: Monday 25 October, 6.00pm to 7.30pm
-
Concept plans now ready
Share Concept plans now ready on Facebook Share Concept plans now ready on Twitter Share Concept plans now ready on Linkedin Email Concept plans now ready linkThe concept plans for the remainder of the Jumping Creek Road upgrade are now complete and we anticipate the detailed design process to be complete by late 2021, with works to commence late 2022.
Throughout the development of the concept plans, Council has obtained feedback from the community and worked closely with the Jumping Creek Road Community reference panel.
Thank you to everyone who had input into this design and we look forward to commencing works on this important project.
The concept design including artists impressions can be viewed here.
-
Works complete, road reopen
Share Works complete, road reopen on Facebook Share Works complete, road reopen on Twitter Share Works complete, road reopen on Linkedin Email Works complete, road reopen linkThe first stage of works along Jumping Creek Road is now complete and the road is now open to through-traffic.
The major reconstruction works of the road between Ringwood-Warrandyte Road and Nelson Drive has been completed to improve safety and accessibility for all road users.
Works included significant drainage infrastructure improvements, creating retaining walls, safety barriers, installing a new pedestrian path and landscaping works to complement the upgraded road.
Thank you to everyone for your patience as we completed these works over the past few months and road detours were in place.
This is an important first step in the Jumping Creek Road upgrade project.
Check out the photos in our gallery.
-
Stage one works nearly complete on Jumping Creek Road
Share Stage one works nearly complete on Jumping Creek Road on Facebook Share Stage one works nearly complete on Jumping Creek Road on Twitter Share Stage one works nearly complete on Jumping Creek Road on Linkedin Email Stage one works nearly complete on Jumping Creek Road linkThe first stage of works is now nearing completion on Jumping Creek Road.
Due to some weather delays and challenges due to the current stage four COVID-19 restrictions, works are currently scheduled to be complete in mid-September 2020 with the road opening to through-traffic soon after.
All excavation works, the relocation of underground services and underground drainage have been completed as has the installation of kerb and channel between Ringwood-Warrandyte Road and Nelson Drive.
The focus over the next couple of weeks will be asphalting the road surface and completing the footpaths along this stretch of road.
Construction works on Jumping Creek Road are being completed in accordance with the Victorian Government’s stage four coronavirus (COVID-19) restrictions currently in place for metropolitan Melbourne.
Thank you to everyone for your patience as we complete these works and road detours are in place. We look forward to re-opening Jumping Creek Road once the upgrade works are complete.
-
Works taking shape along Jumping Creek Road
Share Works taking shape along Jumping Creek Road on Facebook Share Works taking shape along Jumping Creek Road on Twitter Share Works taking shape along Jumping Creek Road on Linkedin Email Works taking shape along Jumping Creek Road linkWorks on stage one of the upgrade of Jumping Creek Road are progressing with construction underway between Ringwood-Warrandyte Road and Nelson Drive in Warrandyte
Since construction started in mid-April works have included re-levelling the road area, which will help to improve sightlines and safety along this section of road.
Excavation works are now nearly completed and many underground services have been relocated.
Works to install new underground drainage pipes are about half way through. We have installed 50 per cent of the kerb and channel and will soon start works on the retaining walls along the side of the road before laying the asphalt.
Works are on track to be completed by the end of August 2020.
For more information, view our June 2020 project update
View some of our progress photos
Follow Project
Project lifecycle
-
Stage one construction
Jumping Creek Road Upgrade has finished this stageRingwood-Warrandyte Road to Nelson Drive was upgraded from 2020 to 2022.
-
Concept design development for remaining stages
Jumping Creek Road Upgrade has finished this stage2022
-
Community consultation on concept design and staging
Jumping Creek Road Upgrade has finished this stage2022 to 2023
-
Community consultation on detailed design
Jumping Creek Road Upgrade has finished this stage2023
-
Construction of recreational trail and safety barriers
Jumping Creek Road Upgrade has finished this stage2023 to 2024
-
Planning and approvals for next construction phase
Jumping Creek Road Upgrade is currently at this stage -
Construction
this is an upcoming stage for Jumping Creek Road UpgradeBeginning after Easter 2025
- Jumping Creek Road, from Homestead Road to the Township
- Yarra Road shared path
- Dudley Road shared path
FAQs
- Where is Jumping Creek Road?
- Why is the upgrade needed?
- What are the benefits of this road upgrade?
- What community consultation has been undertaken for this upgrade project?
- What is the Jumping Creek Road Community Reference Panel?
- What is the purpose of the Jumping Creek Road Development Framework?
- What upgrade works are proposed to be constructed and what improvements are expected?
- What urban design principles were used for this project?
- What will the works involve and will there be impacts while works take place?
- What about emergency service access?
- How will you minimise environmental impacts?
- How will you protect biodiversity including fauna and native vegetation?
- How will you protect water catchments/ hydrology?
- How will you protect and assess cultural and historical heritage assets?