Works have begun on the Dudley Road footpath

Works have started on the Dudley Road footpath reconstruction and will continue until mid-October 2025.

Read our flyer for the latest update.


Construction phases and timing

PHASE LOCATION IN BRIEF

Phase 1

September to October 2025

Property 3 to 35 Dudley Road
  • Footpath construction.
  • Underground drainage installation.
  • Vehicle crossing reconstruction, where required.

Phase 2

October 2025 to October 2026

Property 66 Jumping Creek Road to Homestead Road
  • Underground drainage, kerb and channel installation.
  • Road reconstruction and asphalting.
  • Driveway upgrades, where required.
  • Bus stop upgrades.
  • Line-marking.

Phase 3

From early 2026

Timing to be confirmed.


Jumping Creek Road

Dudley Road intersection to Vine Crescent

  • Traffic light installation.
  • Road and footpath construction.
  • Drainage installation.
  • Bus stop upgrades.
  • Other authority asset works.

Note: There are no traffic signal works at the Yarra Road intersection at this stage.

Share Works have begun on the Dudley Road footpath on Facebook Share Works have begun on the Dudley Road footpath on Twitter Share Works have begun on the Dudley Road footpath on Linkedin Email Works have begun on the Dudley Road footpath link