Jumping Creek Road Upgrade

The Jumping Creek Road Upgrade is a major project to reconstruct the entire length of Jumping Creek Road, from Ringwood-Warrandyte Road in Warrandyte to Homestead Road in Wonga Park.
The Jumping Creek Road Development Framework was endorsed by Council in 2016, and the Jumping Creek Road Masterplan was later endorsed in 2022.
About the project
Where is Jumping Creek Road?
Jumping Creek Road provides an important five kilometre link within Manningham, between Ringwood-Warrandyte Road, Warrandyte and Homestead Road, Wonga Park. It connects the local communities of Warrandyte and Wonga Park and existing employment and retail precincts in Croydon, Chirnside ParkContinue reading
The Jumping Creek Road Upgrade is a major project to reconstruct the entire length of Jumping Creek Road, from Ringwood-Warrandyte Road in Warrandyte to Homestead Road in Wonga Park.
The Jumping Creek Road Development Framework was endorsed by Council in 2016, and the Jumping Creek Road Masterplan was later endorsed in 2022.
About the project
Where is Jumping Creek Road?
Jumping Creek Road provides an important five kilometre link within Manningham, between Ringwood-Warrandyte Road, Warrandyte and Homestead Road, Wonga Park. It connects the local communities of Warrandyte and Wonga Park and existing employment and retail precincts in Croydon, Chirnside Park and Lilydale. It serves as an important transport corridor between the municipalities of Manningham, Maroondah and Yarra Ranges.
The road is located within an environmentally significant landscape with valuable native vegetation and fauna and is also identified as being in a ‘high bushfire risk’ zone.
Why is the upgrade needed?
Jumping Creek Road is a significant local link road that experiences high traffic volumes, carrying more than 8,100 vehicles daily. Projections indicate that this volume will double to 15,000 vehicles daily by 2035.
Between 2012 and 2016, 17 vehicle crashes were reported along Jumping Creek Road. This included seven crashes causing serious injury requiring hospitalisation and one tragically causing fatality. Many of these crashes involved vehicles leaving the road and colliding with objects on the side of the road. These incidents, combined with the deteriorating condition of the road and the challenges faced by pedestrians and cyclists in terms of accessibility, underscore the urgent need for an upgrade.
The Jumping Creek Road upgrade will address these concerns and improve safety for all road users, including motorists, cyclists, and pedestrians. The objective is to deliver safe, sustainable and functional infrastructure that is harmonious with the local landscape.
Jumping Creek Road Community Reference Panel
In January 2017, we established a Jumping Creek Road Community Reference Panel. It consists of residents, relevant local businesses and community group representatives.
The panel is an opportunity for us to provide updates, highlight issues, respond to queries and share ideas with the community, and receive feedback on proposals about the design and reconstruction of Jumping Creek Road.
The panel also considers issues previously raised by the community during the consultation process for the Jumping Creek Road Development Framework.
Questions?
Contact us on 9840 9333 or at manningham@manningham.vic.gov.au.
-
Stage 1 design underway (Ringwood-Warradyte Road to Jumping Creek Bridge)
Share Stage 1 design underway (Ringwood-Warradyte Road to Jumping Creek Bridge) on Facebook Share Stage 1 design underway (Ringwood-Warradyte Road to Jumping Creek Bridge) on Twitter Share Stage 1 design underway (Ringwood-Warradyte Road to Jumping Creek Bridge) on Linkedin Email Stage 1 design underway (Ringwood-Warradyte Road to Jumping Creek Bridge) linkThe preliminary design for the Stage 1 works has been completed in consultation with the Jumping Creek Road Community Reference Panel. A planning permit application for Stage 1A is due to be submitted in February 2018. This is required for vegetation removal, construction of retaining walls and a pedestrian path along this section of Jumping Creek Road.
Construction of Stage 1 will be undertaken in the following stages:
- Stage 1A (commencing June 2018): Ringwood- Warrandyte Road to Nelson Drive (subject to planning approval)
- Stage 1B (commencing in early 2019): Nelson Drive to the approach of the Jumping Creek Bridge
Staging of the works is necessary to ensure that works affecting traffic are limited to minimise impacts during the fire danger season.
-
Jumping Creek Road News Updates
Share Jumping Creek Road News Updates on Facebook Share Jumping Creek Road News Updates on Twitter Share Jumping Creek Road News Updates on Linkedin Email Jumping Creek Road News Updates linkThanks for your feedback
Thank you to everyone who provided feedback on the provision of a footpath on Jumping Creek Road between Yarra Road and Homestead Road. The survey closed on Wednesday 15 November.
The options for consideration include:
- The retention of the existing gravel path along the north side of Jumping Creek Road in its current form
- Construction of an asphalt path on the south side of Jumping Creek Road
- The upgrade of the existing gravel path along the north side of the road to a maximum width of 1.5m, subject to vegetation impacts.
The footpath is a key action of the Jumping Creek Road Development Framework that was adopted by Council in late 2016.
Follow Project
Lifecycle
-
Stage one construction
Jumping Creek Road Upgrade has finished this stageRingwood-Warrandyte Road to Nelson Drive was upgraded from 2020 to 2022.
-
Concept design development for remaining stages
Jumping Creek Road Upgrade has finished this stage2022
-
Community consultation on concept design and staging
Jumping Creek Road Upgrade has finished this stage2022 to 2023
-
Community consultation on detailed design
Jumping Creek Road Upgrade has finished this stage2023
-
Construction of recreational trail and safety barriers
Jumping Creek Road Upgrade has finished this stage2023 to 2024
-
Planning and approvals for next construction phase
Jumping Creek Road Upgrade is currently at this stage -
Construction
this is an upcoming stage for Jumping Creek Road UpgradeBeginning after Easter 2025
- Jumping Creek Road, from Homestead Road to the Township
- Yarra Road shared path
- Dudley Road shared path
FAQs
- What consultation has been undertaken for this upgrade project?
- What are the benefits of this road upgrade?
- What is the purpose of the Jumping Creek Road Development Framework?
- What upgrade works are proposed to be constructed and what improvements are expected?
- What urban design principles were used for this project?
- What will the works involve and will there be impacts while works take place?
- What about emergency service access?
- How will you minimise environmental impacts?
- How will you protect biodiversity including fauna and native vegetation?
- How will you protect water catchments/ hydrology?
- How will you protect and assess cultural and historical heritage assets?
Document Library
-
Flyer - Jumping Creek Road upgrade - Major works commencing - February 2025.pdf (2.99 MB) (pdf)
-
Letter - Next steps for the Jumping Creek Road upgrade - May 2024 (99.8 KB) (pdf)
-
Letter - Notification of night works - patching - February 2024 (4.69 MB) (DOCX)
-
Letter - Recreational Trail Construction Commencement - May 2023 (116 KB) (pdf)
-
Letter - Public Session - May 2023 (120 KB) (PDF)
-
Factsheet - February 2023.pdf (3.85 MB) (pdf)
-
Letter - Public information sessions - February 2023 (96.7 KB) (pdf)
-
Project Plans (14.3 MB) (pdf)
-
Township Design Options (1.38 MB) (pdf)
-
Jumping Creek Road Development Framework - July 2016 (2.76 MB) (pdf)