Stage one works nearly complete on Jumping Creek Road

The first stage of works is now nearing completion on Jumping Creek Road.

Due to some weather delays and challenges due to the current stage four COVID-19 restrictions, works are currently scheduled to be complete in mid-September 2020 with the road opening to through-traffic soon after.

All excavation works, the relocation of underground services and underground drainage have been completed as has the installation of kerb and channel between Ringwood-Warrandyte Road and Nelson Drive.

The focus over the next couple of weeks will be asphalting the road surface and completing the footpaths along this stretch of road.

Construction works on Jumping Creek Road are being completed in accordance with the Victorian Government’s stage four coronavirus (COVID-19) restrictions currently in place for metropolitan Melbourne.

Thank you to everyone for your patience as we complete these works and road detours are in place. We look forward to re-opening Jumping Creek Road once the upgrade works are complete.

Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>