Works taking shape along Jumping Creek Road

Works on stage one of the upgrade of Jumping Creek Road are progressing with construction underway between Ringwood-Warrandyte Road and Nelson Drive in Warrandyte

Since construction started in mid-April works have included re-levelling the road area, which will help to improve sightlines and safety along this section of road.

Excavation works are now nearly completed and many underground services have been relocated.

Works to install new underground drainage pipes are about half way through. We have installed 50 per cent of the kerb and channel and will soon start works on the retaining walls along the side of the road before laying the asphalt.

Works are on track to be completed by the end of August 2020.

For more information, view our June 2020 project update

View some of our progress photos