Stage 1A update – AusNet electrical cable works to get underway

AusNet will be starting works to relocate electrical cables along Jumping Creek Road, between 373 Ringwood-Warrandyte Road and 292 Jumping Creek Road, on Wednesday 14 November.

We’re in the process of finalising the design for stage 1A of the Jumping Creek Road upgrade, which includes lowering a road crest by 1.8 to 2 metres, to improve the lines of sight for traffic on this stretch of the road.

Before the upgrade can begin, electrical cables near the road crest need to be relocated and power poles will need to be removed. This is to reduce roadside hazards and improve safety.

The works being undertaken by AusNet are anticipated to take 5 to 6 weeks to complete. We've been advised that some traffic delays may be experienced during these works. For more information on changing traffic conditions, contact AusNet.

Share Stage 1A update – AusNet electrical cable works to get underway on Facebook Share Stage 1A update – AusNet electrical cable works to get underway on Twitter Share Stage 1A update – AusNet electrical cable works to get underway on Linkedin Email Stage 1A update – AusNet electrical cable works to get underway link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>