Early works on Anderson Street, between Porter Street and Unwin Street
Share Early works on Anderson Street, between Porter Street and Unwin Street on Facebook Share Early works on Anderson Street, between Porter Street and Unwin Street on Twitter Share Early works on Anderson Street, between Porter Street and Unwin Street on Linkedin Email Early works on Anderson Street, between Porter Street and Unwin Street linkThe Templestowe Route Upgrade continues progressing, with the next section of early works commencing 17 July on Anderson Street, between Porter Street and Unwin Street.
This stage follows the completion of the first early works package, on the southern side of Parker Street, between Union Street and the High Street roundabout.
The next section will take around four months to complete depending on weather conditions. It will include drainage, kerb and channel, footpath, and road resurfacing.
Help us build a safer Templestowe Route
What is your experience with Templestowe Route? Do you feel safe and comfortable walking here? How do you find driving along the route?
We want to hear from you. Your experiences and concerns will help inform the upgrade so that we can build a safer Templestowe Route.
Templestowe Route upgrade drop-in information session
Chat with us about the project, view the schematic plans and provide valuable feedback.
đź“… Tuesday 18 July 2023
⏰ 4.00pm to 8.30pm
📍 The auditorium at Manningham Uniting Church, 109 Wood Street, Templestowe 3106Provide your feedback online
Can't make it to the session? That's ok! Have your say by Completing our survey before 4.00pm on Monday, 24 July 2023.
Subscribe to this project to receive updates direct to your inbox.
If you have any questions about these works, please contact us at (03) 9840 9333 or submit an online enquiry at manningham.vic.gov.au/contact-us
-
Upcoming community consulation in July 2023
Share Upcoming community consulation in July 2023 on Facebook Share Upcoming community consulation in July 2023 on Twitter Share Upcoming community consulation in July 2023 on Linkedin Email Upcoming community consulation in July 2023 linkWe’re pleased to announce that we completed the first section of works on Parker Street, on the southern side of the road between Union Street and the High Street roundabout, in May 2023.
The next stage of works will be on the northern side of the road between Union Street and High Street roundabout and along Anderson Street between Porter Street and Unwin Street. We expect to begin these works in July 2023, pending approval from partnering authorities.
These works will include:
- underground drainage
- kerb and channel
- footpaths
- road resurfacing
In the meantime, we’re planning for the works on the remainder of the road. We want to know how we can make this route safer for you.
Templestowe Route drop-in information session
We’re hosting a public information session at Manningham Uniting Church Auditorium on Tuesday, 18 July, from 4.00pm to 8.30pm. We encourage anyone interested in the project to come along and discuss their ideas and provide feedback. Your feedback will help us ensure that the project meets the community's needs.
đź“… Tuesday 18 July 2023
⏰ 4.00pm to 8.30pm
📍 The auditorium at Manningham Uniting Church, 109 Wood Street, Templestowe 3106Can’t make the session? That’s ok! We’re also seeking community feedback through an online survey. Tell us your thoughts about pedestrian connectivity, quality of infrastructure and safety.
Complete the survey by 4.00pm by Monday 24 July 2023.
-
Path Construction delayed
Share Path Construction delayed on Facebook Share Path Construction delayed on Twitter Share Path Construction delayed on Linkedin Email Path Construction delayed linkThe start date on the construction of a path along Parker Street from Union Street to High Street has been delayed due to material supply issues. We expect materials to arrival in April/May and for the project to commence shortly after that.
Once works commence there may be some traffic delays. Please allow extra time for your journey or seek an alternative route during this time.
-
Early works to commence March 2022
Share Early works to commence March 2022 on Facebook Share Early works to commence March 2022 on Twitter Share Early works to commence March 2022 on Linkedin Email Early works to commence March 2022 linkWe are pleased to inform you that works will be commencing shortly to upgrade Templestowe Road. An early works package on the first stage are set to commence in March 2022.
These works will include;
- The construction of a shared path on Parker Street from Union Street to High Street
- Service relocation works where required
- Installation of drainage infrastructure (pits and pipes), kerb and channel;
We are planning to undertake preliminary works which will involve and these works are planned to commence in mid-March 2022.