The Jumping Creek Road Upgrade is a major project to reconstruct the entire length of Jumping Creek Road, from Ringwood-Warrandyte Road in Warrandyte to Homestead Road in Wonga Park.

Questions?

Contact us on 9840 9333 or at manningham@manningham.vic.gov.au.

The Jumping Creek Road Upgrade is a major project to reconstruct the entire length of Jumping Creek Road, from Ringwood-Warrandyte Road in Warrandyte to Homestead Road in Wonga Park.

Questions?

Contact us on 9840 9333 or at manningham@manningham.vic.gov.au.

  • Concept plans now ready

    Share Concept plans now ready on Facebook Share Concept plans now ready on Twitter Share Concept plans now ready on Linkedin Email Concept plans now ready link

    The concept plans for the remainder of the Jumping Creek Road upgrade are now complete and we anticipate the detailed design process to be complete by late 2021, with works to commence late 2022.

    Throughout the development of the concept plans, Council has obtained feedback from the community and worked closely with the Jumping Creek Road Community reference panel.

    Thank you to everyone who had input into this design and we look forward to commencing works on this important project.

    The concept design including artists impressions can be viewed here.

  • Works complete, road reopen

    Share Works complete, road reopen on Facebook Share Works complete, road reopen on Twitter Share Works complete, road reopen on Linkedin Email Works complete, road reopen link

    The first stage of works along Jumping Creek Road is now complete and the road is now open to through-traffic.


    The major reconstruction works of the road between Ringwood-Warrandyte Road and Nelson Drive has been completed to improve safety and accessibility for all road users.


    Works included significant drainage infrastructure improvements, creating retaining walls, safety barriers, installing a new pedestrian path and landscaping works to complement the upgraded road.


    Thank you to everyone for your patience as we completed these works over the past few months and road detours were in place.


    This is an important first step in the Jumping Creek Road upgrade project.


    Check out the photos in our gallery.

  • Stage one works nearly complete on Jumping Creek Road

    Share Stage one works nearly complete on Jumping Creek Road on Facebook Share Stage one works nearly complete on Jumping Creek Road on Twitter Share Stage one works nearly complete on Jumping Creek Road on Linkedin Email Stage one works nearly complete on Jumping Creek Road link

    The first stage of works is now nearing completion on Jumping Creek Road.

    Due to some weather delays and challenges due to the current stage four COVID-19 restrictions, works are currently scheduled to be complete in mid-September 2020 with the road opening to through-traffic soon after.

    All excavation works, the relocation of underground services and underground drainage have been completed as has the installation of kerb and channel between Ringwood-Warrandyte Road and Nelson Drive.

    The focus over the next couple of weeks will be asphalting the road surface and completing the footpaths along this stretch of road.

    Construction works on Jumping Creek Road are being completed in accordance with the Victorian Government’s stage four coronavirus (COVID-19) restrictions currently in place for metropolitan Melbourne.

    Thank you to everyone for your patience as we complete these works and road detours are in place. We look forward to re-opening Jumping Creek Road once the upgrade works are complete.

  • Works taking shape along Jumping Creek Road

    Share Works taking shape along Jumping Creek Road on Facebook Share Works taking shape along Jumping Creek Road on Twitter Share Works taking shape along Jumping Creek Road on Linkedin Email Works taking shape along Jumping Creek Road link

    Works on stage one of the upgrade of Jumping Creek Road are progressing with construction underway between Ringwood-Warrandyte Road and Nelson Drive in Warrandyte

    Since construction started in mid-April works have included re-levelling the road area, which will help to improve sightlines and safety along this section of road.

    Excavation works are now nearly completed and many underground services have been relocated.

    Works to install new underground drainage pipes are about half way through. We have installed 50 per cent of the kerb and channel and will soon start works on the retaining walls along the side of the road before laying the asphalt.

    Works are on track to be completed by the end of August 2020.

    For more information, view our June 2020 project update

    View some of our progress photos

  • Construction underway, road closures in place

    Share Construction underway, road closures in place on Facebook Share Construction underway, road closures in place on Twitter Share Construction underway, road closures in place on Linkedin Email Construction underway, road closures in place link

    The first stage of the Jumping Creek Road reconstruction project is now underway.

    With works starting in mid-April, this important project aims to improve the road’s safety while upgrading the existing infrastructure and increasing connectivity for pedestrians. Weather permitting, the construction of this stage is expected to be complete by the end of August 2020.

    The road is now closed between Yarra Road and Ringwood-Warrandyte Road and will remain closed for the duration of this construction period. Only local resident and emergency vehicle access is permitted during this time. The road closure is in place for the safety of all road users during construction and to allow the works be completed as quickly and efficiently as possible.

    Detours are in place with traffic diverted via Yarra Road and Brysons Road. To prepare for the increased traffic flows along these roads, some preliminary works were completed along the diversion route. Additional road maintenance works, signage and speed control signs are currently being arranged and the condition of the detour routes is being closely monitored.

  • Works to get underway with road closures in place from 21 April 2020

    Share Works to get underway with road closures in place from 21 April 2020 on Facebook Share Works to get underway with road closures in place from 21 April 2020 on Twitter Share Works to get underway with road closures in place from 21 April 2020 on Linkedin Email Works to get underway with road closures in place from 21 April 2020 link

    Construction works will get underway this month on the upgrade of Jumping Creek Road between the Ringwood-Warrandyte Road and Nelson Drive in Warrandyte.

    To allow for the reconstruction of this 350 metre section of road, the road will be closed to through traffic from 21 April 2020 until the end of August.

    Detours will be in place via Yarra Road and Brysons Road during this period. Emergency service vehicle and local access will be maintained at all times.

    This is the first step of construction for the Jumping Creek Road project.

    Coronavirus (COVID-19)

    We understand everyone in our community is responding to the evolving coronavirus (COVID-19) situation.

    At this stage, we do not foresee there are any impacts to the delivery of this road upgrade project.

    The safety of our community is our top priority during this time.

    In Manningham, we are following advice from the Department of Health and Human Services and encourage everyone to practise good hygiene and social distancing in our community.

    For updates on Council services and facilities during this time, visit our website.


  • Construction works to start on Jumping Creek Road

    Share Construction works to start on Jumping Creek Road on Facebook Share Construction works to start on Jumping Creek Road on Twitter Share Construction works to start on Jumping Creek Road on Linkedin Email Construction works to start on Jumping Creek Road link


    Construction on the upgrade of Jumping Creek Road will start in April this year, with the first stage to reconstruct the road between the Ringwood-Warrandyte Road and Nelson Drive in Warrandyte.

    This is the first step of construction for Jumping Creek Road, which ultimately will see the full length of Jumping Creek Road between Ringwood-Warrandyte Road and Homestead Road in Wonga Park upgraded, to improve safety for all road users.

    Works on the initial 350 metre section of Jumping Creek Road include lowering part of the road by more than one metre.

    Due to the construction safety issues associated with these works this section of road will be closed to through traffic during construction, which is anticipated to be completed between early April and the end of August 2020.

    While road closures and detours will be in place for this area, emergency service vehicle and local access will be maintained at all times.

    For more details, view our fact sheet.

  • Stage 1A Planning Permit now advertised

    Share Stage 1A Planning Permit now advertised on Facebook Share Stage 1A Planning Permit now advertised on Twitter Share Stage 1A Planning Permit now advertised on Linkedin Email Stage 1A Planning Permit now advertised link

    The Planning Permit application for stage 1A of the Jumping Creek Road upgrade is now available for public comment.

    The planning application relates to the vegetation removal associated with the upgrade between Ringwood-Warrandyte Road to Nelson Drive.

    All relevant documentation associated with the application is currently available for public inspection:

    Written submissions can be made online via Manningham's Planning Register or via post to Manningham Council, PO Box 1, Doncaster VIC 3108.

    If you intend to make a written submission, you will need to provide your full name and contact details (address, email and phone number during business hours) together with the planning application reference of PLN19/0038.

    Please see Notice of an application for planning permit: PLN19/0038.

    Submissions close on Wednesday 15 May 2019.

  • Service relocation works progressing

    Share Service relocation works progressing on Facebook Share Service relocation works progressing on Twitter Share Service relocation works progressing on Linkedin Email Service relocation works progressing link

    Works to relocate telecommunications, water and gas lines between Ringwood-Warrandyte Road and Nelson Drive are progressing as part of stage 1A of the Jumping Creek Road upgrade.

    These works started in November 2018, over summer some electrical relocation works were delayed due to warm weather.

    While the relocation works are underway, Council is finalising the design of stage 1A of the road upgrade. This will include a planning permit process, which is anticipated to be advertised for public comment during April/May.
  • Stage 1A update – AusNet electrical cable works to get underway

    Share Stage 1A update – AusNet electrical cable works to get underway on Facebook Share Stage 1A update – AusNet electrical cable works to get underway on Twitter Share Stage 1A update – AusNet electrical cable works to get underway on Linkedin Email Stage 1A update – AusNet electrical cable works to get underway link

    AusNet will be starting works to relocate electrical cables along Jumping Creek Road, between 373 Ringwood-Warrandyte Road and 292 Jumping Creek Road, on Wednesday 14 November.

    We’re in the process of finalising the design for stage 1A of the Jumping Creek Road upgrade, which includes lowering a road crest by 1.8 to 2 metres, to improve the lines of sight for traffic on this stretch of the road.

    Before the upgrade can begin, electrical cables near the road crest need to be relocated and power poles will need to be removed. This is to reduce roadside hazards and improve safety.

    The works being undertaken by AusNet are anticipated to take 5 to 6 weeks to complete. We've been advised that some traffic delays may be experienced during these works. For more information on changing traffic conditions, contact AusNet.