Project update - January 2024
Most of the trail between Nelson Drive and the township is complete, including all the works that were scheduled to be done by June 2024. Additional works, including safety barriers, fencing around the bridge area, and an extension of the trail, will be carried out by June 2024.
We are preparing for the project's next stage, which includes the road reconstruction from Vine Crescent to Homestead Road. The project design has already been finalised, and we will soon begin arranging asset relocation and obtaining the necessary third-party approvals for the works. A significant amount of asset relocation is required, which will take some time. Once it is complete, we will begin the next stage of works, likely in early 2025.
We are also in the process of procuring a contract for major patching works, which should begin in early 2024. In the meantime, our team is maintaining the potholes to address any immediate risks.
The major patching works will occur at night and in sections between Nelson Drive and Homestead Road. The total length of this work will be around 1.1 kilometres over a stretch of 5.2 kilometres. The night works aim to reduce any inconvenience to road users and will take approximately two weeks to complete. These dates are subject to change depending on the programming of the Jumping Creek Road upgrade works and weather conditions.
If you have any questions about the Jumping Creek Road upgrade, contact us.