Articles
-
Parker Street works are expected to finish in December 2026
Share Parker Street works are expected to finish in December 2026 on Facebook Share Parker Street works are expected to finish in December 2026 on X (formerly Twitter) Share Parker Street works are expected to finish in December 2026 on Linkedin Email Parker Street works are expected to finish in December 2026 linkRead our flyer for the latest information, including details about the works depicted in the map below.
In summary:
- Parker Street works are on schedule and are expected to finish in December 2026.
- Additional works on Atkinson and Porter Streets will start from 26 October 2026.The next phase Of works on James and Swilk Streets are planned to Start in 2027 once a contractor is appointed.
Templestowe Route Upgrade works overview

Read our flyer for the latest information, including details about the works depicted in the map below.
In summary:
- Parker Street works are on schedule and are expected to finish in December 2026.
- Additional works on Atkinson and Porter Streets will start from 26 October 2026.The next phase Of works on James and Swilk Streets are planned to Start in 2027 once a contractor is appointed.
Templestowe Route Upgrade works overview

-
Parker Street works remain on track for completion
Share Parker Street works remain on track for completion on Facebook Share Parker Street works remain on track for completion on X (formerly Twitter) Share Parker Street works remain on track for completion on Linkedin Email Parker Street works remain on track for completion linkRead our flyer for the latest information, including details about the works depicted in the map below.
In summary:
- Parker Street works remain on track for completion in December 2026.
- Additional works on Porter and Atkinson streets are scheduled to begin in late 2026.
- Works on James and Swilk streets are planned to start in early 2027, following contractor appointment.
Templestowe Route Upgrade works overview

Read our flyer for the latest information, including details about the works depicted in the map below.
In summary:
- Parker Street works remain on track for completion in December 2026.
- Additional works on Porter and Atkinson streets are scheduled to begin in late 2026.
- Works on James and Swilk streets are planned to start in early 2027, following contractor appointment.
Templestowe Route Upgrade works overview

-
Additional works on Atkinson Street commencing in late 2026
Share Additional works on Atkinson Street commencing in late 2026 on Facebook Share Additional works on Atkinson Street commencing in late 2026 on X (formerly Twitter) Share Additional works on Atkinson Street commencing in late 2026 on Linkedin Email Additional works on Atkinson Street commencing in late 2026 linkRead our flyer for the latest information.
In summary:
- Parker Street works have resumed.
- Additional works on Atkinson Street are scheduled to commence in late 2026.
- The next phase of works on James and Swilk Streets is expected to start in early 2027 once a contractor is appointed.
Read our flyer for the latest information.
In summary:
- Parker Street works have resumed.
- Additional works on Atkinson Street are scheduled to commence in late 2026.
- The next phase of works on James and Swilk Streets is expected to start in early 2027 once a contractor is appointed.
-
Parker Street works resuming in late June
Share Parker Street works resuming in late June on Facebook Share Parker Street works resuming in late June on X (formerly Twitter) Share Parker Street works resuming in late June on Linkedin Email Parker Street works resuming in late June linkRead our flyer for the latest information, including details about the works depicted in the map below.
In summary:
- Nightworks and resurfacing on Parker Street are complete.
- Parker Street works will resume in late June.
- Additional kerb and channel works on Atkinson and Porter Street are scheduled to commence in late 2026.
- The next phase of works on James and Swilk Streets is expected to start in early 2027 following a tender.
Upcoming works:

Read our flyer for the latest information, including details about the works depicted in the map below.
In summary:
- Nightworks and resurfacing on Parker Street are complete.
- Parker Street works will resume in late June.
- Additional kerb and channel works on Atkinson and Porter Street are scheduled to commence in late 2026.
- The next phase of works on James and Swilk Streets is expected to start in early 2027 following a tender.
Upcoming works:

-
Key milestone achieved as Templestowe Route Upgrade progresses
Share Key milestone achieved as Templestowe Route Upgrade progresses on Facebook Share Key milestone achieved as Templestowe Route Upgrade progresses on X (formerly Twitter) Share Key milestone achieved as Templestowe Route Upgrade progresses on Linkedin Email Key milestone achieved as Templestowe Route Upgrade progresses linkThe Templestowe Route Upgrade has reached a major milestone, with works on Anderson Street now complete.
The upgraded section provides safer and more accessible connections for pedestrians and cyclists, forming a vital link between key destinations as construction continues across the route.
Manningham Mayor, Cr Jim Grivas said the project is delivering tangible benefits for the community while prioritising the environment.
“We’re seeing strong progress along the Templestowe Route, with completed sections already benefiting the community.
“At Ruffey Creek, we’ve renewed the footbridge to improve visibility, safety and accessibility, while also installing a new porous footpath that allows rainwater to naturally filter into surrounding tree roots,” Cr Grivas said.

“This has fantastic environmental outcomes that support tree health while reducing water runoff.
“These upgrades are not only improving connections across Manningham, but also demonstrating how infrastructure can be delivered in a way that respects and enhances our natural environment.
“Construction will continue along the remaining sections of the route, completing the missing links and delivering a safer, more connected and sustainable transport network for residents and visitors,” Cr Grivas said.
The next phase of works is scheduled to commence in early 2027 along Parker and Swilk Streets.The Templestowe Route Upgrade has reached a major milestone, with works on Anderson Street now complete.
The upgraded section provides safer and more accessible connections for pedestrians and cyclists, forming a vital link between key destinations as construction continues across the route.
Manningham Mayor, Cr Jim Grivas said the project is delivering tangible benefits for the community while prioritising the environment.
“We’re seeing strong progress along the Templestowe Route, with completed sections already benefiting the community.
“At Ruffey Creek, we’ve renewed the footbridge to improve visibility, safety and accessibility, while also installing a new porous footpath that allows rainwater to naturally filter into surrounding tree roots,” Cr Grivas said.

“This has fantastic environmental outcomes that support tree health while reducing water runoff.
“These upgrades are not only improving connections across Manningham, but also demonstrating how infrastructure can be delivered in a way that respects and enhances our natural environment.
“Construction will continue along the remaining sections of the route, completing the missing links and delivering a safer, more connected and sustainable transport network for residents and visitors,” Cr Grivas said.
The next phase of works is scheduled to commence in early 2027 along Parker and Swilk Streets. -
Nightworks and resurfacing on Parker Street are complete
Share Nightworks and resurfacing on Parker Street are complete on Facebook Share Nightworks and resurfacing on Parker Street are complete on X (formerly Twitter) Share Nightworks and resurfacing on Parker Street are complete on Linkedin Email Nightworks and resurfacing on Parker Street are complete linkRead our flyer for the latest construction update with more information, including details about the works depicted in the map below.
In summary:
- Nightworks and resurfacing on Parker Street are complete.
- Pedestrian-operated signal crossing and electronic speed sign installation on James and Anderson Street is progressing.
- We’re renewing the Ruffey Creek footbridge boardwalk on Parker Street.
- There is reduced construction activity onsite with Parker Street works on hold until June.
- Temporary fencing will be in place until works resume.

Read our flyer for the latest construction update with more information, including details about the works depicted in the map below.
In summary:
- Nightworks and resurfacing on Parker Street are complete.
- Pedestrian-operated signal crossing and electronic speed sign installation on James and Anderson Street is progressing.
- We’re renewing the Ruffey Creek footbridge boardwalk on Parker Street.
- There is reduced construction activity onsite with Parker Street works on hold until June.
- Temporary fencing will be in place until works resume.

-
Nightworks scheduled for resurfacing on Parker Street
Share Nightworks scheduled for resurfacing on Parker Street on Facebook Share Nightworks scheduled for resurfacing on Parker Street on X (formerly Twitter) Share Nightworks scheduled for resurfacing on Parker Street on Linkedin Email Nightworks scheduled for resurfacing on Parker Street linkRead our flyer for the latest construction update with more information, including details about the nightworks depicted in the map below.
In summary:
- Mahoney Street will be closed from 3 to 6 March for road reconstruction.
- Nightworks are scheduled from 10 to 12 March for resurfacing on Parker Street.
- We’re installing a pedestrian operated signal crossing and electronic speed sign on Anderson Street.

Read our flyer for the latest construction update with more information, including details about the nightworks depicted in the map below.
In summary:
- Mahoney Street will be closed from 3 to 6 March for road reconstruction.
- Nightworks are scheduled from 10 to 12 March for resurfacing on Parker Street.
- We’re installing a pedestrian operated signal crossing and electronic speed sign on Anderson Street.

-
Construction works have resumed
Share Construction works have resumed on Facebook Share Construction works have resumed on X (formerly Twitter) Share Construction works have resumed on Linkedin Email Construction works have resumed linkRead our flyer for the latest construction update with more information.
In summary:
- Construction works have resumed following the pause over the festive season.
- We’re installing a pedestrian operated signal crossing and electronic speed sign on Anderson Street.
- Traffic bollards remain in place to guide traffic and protect newly reinstated nature strips.
Service disruptions:
- A temporary power outage between 4 to 6 hours will be required to complete the installation of bus stop lighting and electronic speed signs.
- The works and timings will be dependent on approval from the Department of Transport and Planning.
- United Energy will provide more detailsContinue reading
Read our flyer for the latest construction update with more information.
In summary:
- Construction works have resumed following the pause over the festive season.
- We’re installing a pedestrian operated signal crossing and electronic speed sign on Anderson Street.
- Traffic bollards remain in place to guide traffic and protect newly reinstated nature strips.
Service disruptions:
- A temporary power outage between 4 to 6 hours will be required to complete the installation of bus stop lighting and electronic speed signs.
- The works and timings will be dependent on approval from the Department of Transport and Planning.
- United Energy will provide more details including dates once confirmed.
- There are currently no planned outages for other services.
- We’re working closely with service providers to avoid unexpected disruptions. In the unlikely event of an interruption, the service provider will respond as usual.
-
New signal crossing and speed sign on Anderson Street
Share New signal crossing and speed sign on Anderson Street on Facebook Share New signal crossing and speed sign on Anderson Street on X (formerly Twitter) Share New signal crossing and speed sign on Anderson Street on Linkedin Email New signal crossing and speed sign on Anderson Street linkRead our flyer for the latest construction update with more information.
In summary:
- We’re installing a pedestrian operated signal crossing and electronic speed sign on Anderson Street.
- Construction works will pause from 22 December 2025 to 5 January 2026. Shops, roads and pedestrian paths remain open.
- Traffic bollards are in place to guide traffic and protect newly reinstated nature strips.
- For assistance during this time, contact 9840 9333.
Read our flyer for the latest construction update with more information.
In summary:
- We’re installing a pedestrian operated signal crossing and electronic speed sign on Anderson Street.
- Construction works will pause from 22 December 2025 to 5 January 2026. Shops, roads and pedestrian paths remain open.
- Traffic bollards are in place to guide traffic and protect newly reinstated nature strips.
- For assistance during this time, contact 9840 9333.
-
Update on Parker Street and Anderson Street works
Share Update on Parker Street and Anderson Street works on Facebook Share Update on Parker Street and Anderson Street works on X (formerly Twitter) Share Update on Parker Street and Anderson Street works on Linkedin Email Update on Parker Street and Anderson Street works linkThe Parker Street works started on 18 September and the Anderson Street works continue to run on schedule.
Read our flyer for more information and to find out more about these upcoming road closures.
Continue readingAnderson Street road closure - night works
13 to 18 October 2025- Final asphalting on Anderson Street, James Street to Unwin Street.
- Work in different sections will be completed each night.
- Driveways will be blocked for one night.
- Pedestrian access will be maintained at all times during the works.
- Business access may be impacted – we’ll contact you to make a plan.
Parker Street road closure The Parker Street works started on 18 September and the Anderson Street works continue to run on schedule.
Read our flyer for more information and to find out more about these upcoming road closures.
Anderson Street road closure - night works
13 to 18 October 2025- Final asphalting on Anderson Street, James Street to Unwin Street.
- Work in different sections will be completed each night.
- Driveways will be blocked for one night.
- Pedestrian access will be maintained at all times during the works.
- Business access may be impacted – we’ll contact you to make a plan.
Parker Street road closure - night works
13 to 18 October 2025- We will be working in different sections each night.
- Installing crossover drainage.
- Driveways will be accessible from one direction only.
- Pedestrian access will be maintained.
- Business access will be maintained at all times during the works.