Works continuing at Tunstall Square
Works are progressing on the sreetscape upgrade at Tunstall Square.
The final asphalt layer for the footpath area has been completed at the front of the shops. Demolition and footpath preparation, construction of kerb and channel, installation of drainage pipes and pits, central plaza bluestone pavers and exposed aggregate is continuing.
Works will continue until 9 April before breaking for Easter and re-commencing on 15 April.