Tuckers Road Project update May 2022
We are pleased to inform you that despite all supply and resourcing issues we have managed to still stay within the project time frame so far.
Below is a summary of the project's physical progress:
- The Eastern footpath is 95% complete;
- Drainage works are 95% Completed;
- Kerb and Chanel's works are 75% Completed including the indented carparks;
- The Western Shared Path is 20% completed;
- Roundabout works set out completed, Kerb works Planned to be started Mid-May;
- Earthworks are Planed to be started immediately after the Kerb, Shared path, footpath, and roundabout works are completed.
Share Tuckers Road Project update May 2022 on Facebook
Share Tuckers Road Project update May 2022 on Twitter
Share Tuckers Road Project update May 2022 on Linkedin
Email Tuckers Road Project update May 2022 link
Consultation has concluded