27 March → 29 April 2020
Stage 2 Engagement on Draft Concept Plan
July 2020
Final concept plan delivered
Final concept plan to be endorsed by Council.
July 2020
Concept plan approved by Council
August 2020 → October 2021
Detailed design for the new park and public tender for demolition works
November 2021 → January 2022
Demolition of houses
February 2022 → August 2023
Finalise construction documentation and public tender for construction works
September 2023 → April 2024
Construction of park
May 2024
The park will be open to the public