The concept plan for a new park on Hepburn Road in Doncaster has been approved by Council and will now move into the detailed design phase. The concept design has been developed in response to community feedback and will include outdoor seating, a BBQ area, a drinking fountain, public art, large open lawn areas, a playspace, nature play, canopy tree planting, bike hoops and more. The new park is designed to provide additional open space to local residents living, working or visiting the Doncaster Hill area.

View the final concept plan here.

Project timelines for upcoming key stages are:

  • January/February 2022 - Demolition of the houses at 9, 11, 13 and 15 Hepburn Road (approximately 2 month duration)
  • Early 2023 - Construction to commence on the new park (approximately 8 months duration)

For more information please see the FAQs here.

This project was identified as an important community initiative in the Doncaster Hill Strategy 2002 (revised 2004).

Location of Doncaster Hill's newest park
The new park will be located on Hepburn Road in Doncaster, between Walker Street and Gifford Street where we have acquired several properties to make way for the new space.

For more information:

Email: manningham@manningham.vic.gov.au

Phone: 9840 9333

The concept plan for a new park on Hepburn Road in Doncaster has been approved by Council and will now move into the detailed design phase. The concept design has been developed in response to community feedback and will include outdoor seating, a BBQ area, a drinking fountain, public art, large open lawn areas, a playspace, nature play, canopy tree planting, bike hoops and more. The new park is designed to provide additional open space to local residents living, working or visiting the Doncaster Hill area.

View the final concept plan here.

Project timelines for upcoming key stages are:

  • January/February 2022 - Demolition of the houses at 9, 11, 13 and 15 Hepburn Road (approximately 2 month duration)
  • Early 2023 - Construction to commence on the new park (approximately 8 months duration)

For more information please see the FAQs here.

This project was identified as an important community initiative in the Doncaster Hill Strategy 2002 (revised 2004).

Location of Doncaster Hill's newest park
The new park will be located on Hepburn Road in Doncaster, between Walker Street and Gifford Street where we have acquired several properties to make way for the new space.

For more information:

Email: manningham@manningham.vic.gov.au

Phone: 9840 9333

  • Construction Phase

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    We are about to start demolition of the houses of 9, 11, 13 and 15 on Hepburn Road to enable the construction of a new park. Please note, there may be some noise disruption, however we endeavour to minimise the impacts.

    The safety of our community is our top priority during this time and Manningham will continue to follow the advice from the Department of Health and Human Services about coronavirus (COVID-19).

  • Stage 2 Engagement has concluded

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Thank you so much for giving us your feedback on the concept plans. We are encouraged by the number of very positive responses as well as the constructive criticisms. We will get back to you soon with feedback on what you have told us as we finalise our plans for this new urban park.

Page last updated: 10 Jan 2023, 11:51 AM